In Grúas y Equipos García we were supporting the Chapultepec District work in the Guadalajara ZMG, with the excavation with a pile driver, and maneuvering with a 350-ton Liebherr crane to lower a 48-ton dredge.
The excavation was carried out with a 36-ton pile-driver, in order to place a 48-ton dredge with a Liebherr LTM 1350-6.1 crane configured with a 25-meter hydraulic boom at a working radius of 12 meters, with 60 tons of counterweight.